Planning a renovation

Kitchen renovation checklist: plan it in the right order

A kitchen pulls in more trades than any other room. The decisions to make before you order, the order of work from strip-out to worktops and appliances, the checks at each stage and what to collect before the last payment.

A kitchen checklist: layout agreed and sockets and plumbing ticked, worktop still to measure
Contents

Key points

  • Plan a kitchen in this order: decide the layout and appliances, measure, order units, strip out, first fix plumbing, gas and electrics, plaster, lay the floor, fit units, template and fit worktops, then connect, test and finish.
  • Fix the layout and every appliance before first fix, because the positions of sockets, pipes, waste and the extractor depend on them.
  • Which? says labour is roughly 20% to 30% of a kitchen's final cost if you do none of the installation yourself (BCIS data, April 2026).
  • Order units early: lead times can run to months, and at the villa in this guide the kitchen had a three month lead time.
  • Gas work must be done by a Gas Safe registered engineer, and in England and Wales notifiable electrical work needs a registered electrician or building control.

What is the right order for a kitchen renovation?

A kitchen renovation goes in this order: decide the layout and appliances, measure and order the units, strip out, run first fix plumbing, gas and electrics, plaster, lay the floor, fit the units, template and fit the worktops, then connect the sink and appliances, finish the electrics, tile and decorate. Each stage depends on the one before.

A kitchen pulls in more trades than any other room: a plumber, an electrician, often a gas engineer, a plasterer, a floor layer, the fitter and a worktop maker, all working around units that may take months to arrive. This checklist covers the decisions to make first, the order of work, the checks at each stage and what to collect before you pay. For what it costs, see our kitchen renovation budget, which takes you line by line.

Before you order: the decisions

Every pipe, cable and socket position follows from these, so they come first.

  • How you cook, eat and use the room, and what does not work now
  • Measurements: walls, ceiling height, windows, doors, radiators, pipes and the meter or boiler
  • Layout: keep or move the sink, hob and oven
  • Every appliance chosen, with its size, power and installation instructions
  • Extractor type and where it vents, inside or through a wall
  • Sockets: worktop, appliance, island and any USB points, with heights
  • Lighting: ceiling, under-cabinet and over the table, and how each is switched
  • Gas or electric hob, and whether the gas supply moves
  • Water: sink, dishwasher, washing machine, fridge water supply, boiling water tap
  • Floor: what it is, and whether it goes under the units or stops at them
  • Worktop material, which usually has to be templated after the units are in
  • Storage, bins and recycling, and where everything lives

Tip

Moving the sink or hob moves the waste, water and gas, and often the electrics. Which? (April 2026) notes that one kitchen retailer told it to expect around 30% of the budget to go on plumbing, flooring, electrics and other expenses beyond the units.

Planning the trades and orders

  1. Write the scope. The design, every appliance and its position, and what is removed. Our scope of works guide shows how.
  2. Get at least three quotes. On the same scope, with each trade shown. Our guide to comparing builders' quotes shows how to line them up.
  3. Agree who does what. Who fits the units, who connects the appliances, who makes good the walls, who removes the waste.
  4. Check the specialists. Gas work by a Gas Safe registered engineer; electrical work by a registered electrician.
  5. Order the units and appliances. Note each lead time and delivery date, and where everything will be stored when it arrives.
  6. Agree the contract and payment stages. Tie payments to stages of work, and keep a significant part until the end. Our guide to how to pay a contractor covers this.
  7. Plan a temporary kitchen. A microwave, kettle and fridge in another room, and somewhere to wash up.

Which? says labour is roughly 20% to 30% of the final cost of a kitchen if you do none of the installation yourself, based on BCIS data.

The order of work, stage by stage

Example renovation finance: estimates, paid amounts and agreed costs still to payCosts & spending in Mekozo, close up: whole project £8,300 plus one unpriced item, paid £2,000, still to pay £3,500, £12,000 in the plan

Mekozo's Costs & spending view shows the renovation's costs room by room or by piece of work, with what is paid and still to pay, so the kitchen's orders and fitting each have a line.

Try it free for 30 days, no card needed
StageWhat happensCheck before moving on
1. Protect and strip outWater, gas and power isolated; old units, appliances and tiles removedWalls and floor exposed; services capped safely
2. Building workWalls moved, openings made, lintels fitted, repairsStructure signed off where needed
3. First fix plumbing and gasWater, waste and gas run to the new positionsPositions match the plan and appliance instructions; pressure tested
4. First fix electricsCircuits, sockets, cooker supply, lighting and extractor cablingPositions match the plan; registered electrician
5. Extractor and ductingDucting and any hole through the wallRoute and outlet agreed and sealed
6. PlasteringWalls and ceiling made goodDry before tiling or painting
7. FloorLaid before or after the units, as agreedLevel; protected from the fitting that follows
8. Fit the unitsBase, wall and tall units fitted and levelledLevel, square and secure; doors aligned
9. WorktopsTemplated and fitted; sink and hob cut-outsJoints tight, cut-outs correct
10. ConnectSink, tap, appliances, hob and extractor connectedEverything working; no leaks; gas tested
11. Second fix electricsSockets, switches, lights; testingAll working; certificate issued
12. Splashback, sealant and decoratingTiling or panels, silicone, paintSealant cured; room clean
13. Snagging and handoverFaults listed and fixedEvery item closed; documents collected

Watch out

Stone and composite worktops are usually measured once the units are in, then made, then fitted. Ask how long that gap is, because the sink and hob may not work until the worktops are fitted.

Planning the kitchen programme

There is no reliable published average, because a like-for-like replacement and a new layout with building work are different jobs. Ask each fitter for a written programme showing every trade and the gaps for plaster drying and worktop templating. The wait before work starts, while units are made, is often longer than the work itself. Our guide to the renovation schedule covers keeping a programme on track.

Country rules

The order of work is the same everywhere. Who may do the gas, electrical and plumbing work, and what needs approval, differ.

In the UK (England and Wales)

GOV.UK lists replacing fuse boxes and connected electrics, installing or replacing a heating system, and replacing windows and doors among alterations that might need building regulations approval. Electrical Safety First explains that in England and Wales some electrical work is notifiable, such as adding a new circuit or replacing a consumer unit, and must be done by a registered electrician who certifies it, or be notified to building control. Gas work must be done by a Gas Safe registered engineer. Scotland and Northern Ireland have their own rules.

In Italy

On the villa that Mekozo's founder, Jonathan Smith, films for Operation Sicily, the kitchen came after the room had been replanned with new lintels and the electrics finished. Ask your geometra whether moving walls, openings or services needs a notification before work starts.

Elsewhere

Check with the local building department which work needs a permit and who may connect gas and electrics.

On the Operation Sicily villa

From the villa in Sicily. Before the kitchen could go in, the room was replanned: the old double glass doors were removed and the opening reconfigured, which meant new lintels (the real timeline of the villa). Jonathan core drilled through a stone wall for the extractor (Episode 48). When the kitchen designer flagged that the elbows on the waste pipes he had fitted could cause a problem for the fitter, he took them off and cut back the risers against the wall (Episode 75). The units had been ordered and paid for months earlier because of a three month lead time, and by the time the fitters arrived the floor was tiled and grouted and the last sockets were in. After fitting, only the tap and the sink trap were left to do (Episode 92). Every job was ready before the trade after it arrived, which is what this checklist is for.

Playing loads YouTube’s external player.

Watch directly on YouTube ↗

Before the final payment

Walk the finished kitchen with the fitter and test everything. Our snagging list guide shows how to record each fault so it is fixed and closed.

  • Every door and drawer opens, closes and lines up
  • Units level and fixed; plinths and end panels on
  • Worktop joints tight, edges sealed, sink and hob cut-outs correct
  • Taps run hot and cold; no leaks under the sink or at appliances
  • Dishwasher and washing machine run a cycle without leaks
  • Hob, oven and extractor working; gas installation checked
  • Every socket and light working; certificate received
  • Splashback, sealant and decorating finished
  • Guarantees, appliance manuals and registrations collected
  • Any extras agreed in writing and priced before the work was done, as our guide to variations and extras explains

Keep the invoices, payments and guarantees together. An invoice is the bill for agreed work; record it, then the payment against it. Keeping the agreed price, invoices and payments apart shows you what is still to pay.

The full kitchen renovation checklist

Plan

  • Use, measurements and layout decided
  • Appliances chosen and their installation needs checked
  • Socket, lighting, water, waste and gas positions marked
  • Scope written and three quotes compared
  • Trades and responsibilities agreed; contract and payment stages signed
  • Units and appliances ordered with delivery dates; contingency set (see our guide to renovation contingency)

Build

  • Strip-out and building work done
  • First fix plumbing, gas and electrics in the agreed positions
  • Extractor route made; plastering dry
  • Floor laid as agreed
  • Units fitted; worktops templated and fitted
  • Appliances connected and second fix electrics tested

Finish

  • Splashback, sealant and decorating done
  • Snagging list closed
  • Certificates, guarantees and manuals collected
  • Final payment made

Planning a bathroom too? Our bathroom renovation checklist follows the same approach, and our home renovation checklist fits both into the whole-house order. For the wider plan, see our guide to planning a renovation room by room, and to keep the stages, orders and payments together, see the renovation budget tracker and how to build a whole-project budget in Mekozo.

This checklist explains a planning method. It is not professional advice; follow your products' installation instructions and use qualified trades for gas, plumbing and electrical work.

Questions people ask

What order do you renovate a kitchen in?

Decide the layout and appliances, then order the units. Strip out, make repairs, run first fix plumbing, gas and electrics, then plaster and lay the floor if it goes under the units. Fit the units, template and fit the worktops, connect the sink, appliances and second fix electrics, then tile the splashback and decorate.

How do I plan a kitchen renovation?

Start with how you cook and use the room, measure it, and decide whether the sink, hob and oven stay where they are. Choose every appliance before the design is final, write a scope for the fitters, compare at least three quotes and order the units in time for the start date. Plan where you will cook while it is out of action.

How long does a kitchen renovation take?

It depends on the scope, lead times and the trades, so ask each fitter for a written programme. The longest wait is often before work starts, while units are made and delivered. Moving the layout, new electrics, plastering, a new floor and worktops that must be templated after the units are fitted all add time on site.

Should the floor go down before or after kitchen units?

Either can work, so agree it with your fitter for the floor you have chosen. Laying the floor first gives a continuous finish and makes changing units later easier, but costs more flooring; fitting units first saves material but ties the layout to the floor. On the Operation Sicily villa the floor was tiled and grouted before the fitters arrived.

Do I need building regulations approval for a new kitchen?

Replacing units like for like usually does not, but work around a kitchen can. GOV.UK lists replacing fuse boxes and connected electrics, installing or replacing a heating system, and replacing windows and doors among jobs that might need approval in England and Wales. Gas work must be done by a Gas Safe registered engineer.

Sources

  1. Which?, How much does a new kitchen cost in 2026? (BCIS data; unit prices collected May 2025) · 26 April 2026
  2. GOV.UK, Building regulations approval: when you need approval · Updated 20 October 2026
  3. Electrical Safety First, What is Part P of the building regulations? · Checked 18 November 2026
  4. Gas Safe Register, Gas safety information for home buyers and sellers · Checked 18 November 2026
  5. Operation Sicily, Episode 92: Italian kitchen reveal at my Sicilian villa · Checked 18 November 2026
  6. Operation Sicily, Episode 75: Second fix electrics and marking out a rainwater tank · Checked 18 November 2026
  7. Operation Sicily, Episode 48: Core drilling a stone wall for a kitchen extractor fan · Checked 18 November 2026
  8. Operation Sicily, The real timeline of a Sicilian villa renovation · Checked 18 November 2026
Jonathan Smith opening the gate of the villa in Sicily

About the author:

Jonathan Smith is the founder of Mekozo and Operation Sicily. Jonathan bought an abandoned villa in Sicily and is rebuilding it on camera, every week. Mekozo is the app Jonathan built to keep that renovation's money in one picture.

Related from Operation SicilyThe real timeline of a Sicilian villa renovation

Real renovation experience and regional guidance from Operation Sicily.

Blog

Related reading

A bathroom checklist: pipes and drains and waterproofing ticked, fan and lighting still to check
Planning a renovation

Bathroom renovation checklist: the order of work, step by step

A bathroom is a small room with a long list of trades in a strict order. The decisions to make before anyone starts, the sequence of work from strip-out to silicone, the checks at each stage and what to collect before the last payment.

Plan a renovation in order: scope, quotes, budget and schedule
Planning a renovation

Home renovation checklist: plan it in the right order

A renovation goes better when the decisions come in the right order. A phase-by-phase checklist from first idea to handover: what to decide, what to check, who to book and what order the work goes in, with the sources behind each step.

All Blog posts →