Renovation work underway

Renovation schedule: plan the order of works, step by step

A renovation schedule is more than a list of dates. How to build one from the jobs, their dependencies, lead times and decision dates, and how to keep it on track when something slips.

A renovation schedule: strip out and first fix done, plaster and finish to come
Contents

Key points

  • A renovation schedule lists every job in order, with how long it takes, what it depends on, who does it and when the materials and decisions are needed.
  • Build it backwards from dependencies: services before plaster, plaster before floors and kitchens, and anything with a long lead time ordered early.
  • Add decision dates for you, not just work dates for the trades; late choices are one of the commonest causes of delay.
  • Hold buffers for drying times, inspections, deliveries and the weather, and keep notice periods for neighbours and approvals in the plan.
  • Review the schedule every week against what has actually happened, and agree any change to the dates in writing.

How do you plan a renovation schedule?

Plan a renovation schedule in six steps: list every job room by room, work out what each job depends on, put them in order, give each a duration and an owner, add order dates for long lead items and decision dates for you, then hold buffers for drying, inspections and deliveries. Review it every week against what has actually happened.

A schedule is not a promise that nothing will slip. It is a way of seeing, early, what a slip will knock on to. When the plasterer is a week late, the schedule tells you whether the kitchen fitters need moving, and whether the tiles should be delivered later. This guide shows how to build one and keep it useful. For the full order of works on a whole house, see our guide to a full house renovation.

What goes into a renovation schedule

Each line in a schedule answers six questions.

ColumnQuestion it answersExample
JobWhat is being done, and where?Bathroom: first fix plumbing
Depends onWhat must be finished first?Floor up; layout agreed
WhoWhich trade or person?Plumber
DurationHow long, in working days?3 days
Materials and lead timeWhat must be on site, and when must it be ordered?Shower valve: order 2 weeks ahead
Decision neededWhat do you have to decide, and by when?Shower position: by 1 March

Add start and finish dates once the order is set, and a status column for when work begins.

Step 1: list every job, room by room

Start from your scope of works. Go room by room and write every job, including the small ones that are easy to forget: removing radiators before plastering, boxing in pipes, fitting door linings, sealing round the bath. Then add the whole-house jobs, such as the rewire, heating and roof. Our guide to writing a scope of works is a good starting list.

Tip

Split big jobs into the visits the trade will actually make. An electrician usually comes at least twice: first fix while walls are open, second fix after plastering. Each visit is its own line.

Step 2: work out what depends on what

This is the heart of the schedule. Most delays come from a job that cannot start because something before it is not finished.

The general pattern for most renovations:

  1. Structure and weather: structural repairs, roof, and windows or temporary boarding.
  2. Strip out and first fix: old fittings removed; new cables, pipes, heating and drains run while walls and floors are open.
  3. Inspections: any building control or other checks needed before the work is covered.
  4. Plaster and screed: walls and floors closed, then left to dry.
  5. Second fix: sockets, switches, radiators, sanitaryware connected.
  6. Kitchens, bathrooms and flooring: fitted once the rooms are dry and finished.
  7. Decoration: last, once the dust has stopped.

Some jobs can overlap in different rooms; others must wait for drying, testing or inspection.

Watch out

The most expensive schedule mistake is closing a wall too early. Once plaster or tiles go on, any cable, pipe or bracket you forgot means opening it up again.

Step 3: add durations, owners and buffers

Ask each trade how long their part will take and write it in working days. Then add the time between jobs that nobody is paid for, but which the schedule still needs:

  • Drying times for plaster, screed and some adhesives.
  • Inspections, which have to be booked and may not happen the day you want.
  • Deliveries, which arrive on a day, not an hour.
  • Weather, for any outside work.
  • Holidays and trade availability, including your own.

In the UK

The Health and Safety Executive says homeowners can help keep a job safe by allowing sufficient time and money in the agreed contract for the work to be carried out safely. A schedule with no slack pushes trades to rush.

Step 4: add lead times and notice periods

Some things have to be started long before the work that needs them.

ItemWhy it needs planning early
Made to measure windows and doorsMeasured, made and delivered before fitting
KitchensDesigned, ordered and made, often months ahead
Bathroom fittings, tiles and flooringStock runs out; batches should match
Skips, scaffolding and parking permitsBooked ahead, sometimes with council approval
Approvals and inspectionsApplications take time to process
Neighbours' noticeSome work needs formal notice before it starts

In the UK (England and Wales)

Under the Party Wall etc Act 1996, the government's explanatory booklet says work to a party wall needs two months' notice, and excavating near a neighbour's property or building on the line of junction needs one month's notice. If your job is covered, those weeks belong at the start of the schedule.

Step 5: add your decision dates

Builders often wait on homeowners more than homeowners realise. A tile not chosen, a socket position not confirmed or a kitchen layout still changing can stop a trade on site.

For every choice the work depends on, write a "decide by" date in the schedule, well before the job that needs it:

  • Layout of kitchen and bathroom: before first fix
  • Socket, switch and light positions: before electrical first fix
  • Radiator positions and sizes: before heating first fix
  • Tiles, flooring and sanitaryware: before their lead time starts
  • Paint colours: before decorators are booked
  • Door handles, worktops, taps: before second fix and fitting

Tip

Keep a separate list of open questions and decisions, with who needs to answer and by when. Questions left in a message thread are how a two-day decision turns into a two-week delay.

Step 6: track it every week

Example renovation finance: estimates, paid amounts and agreed costs still to payCosts & spending in Mekozo, close up: whole project £8,300 plus one unpriced item, paid £2,000, still to pay £3,500, £12,000 in the plan

Mekozo's Costs & spending view shows the renovation's costs by room or by piece of work, with what is paid and still to pay, so each stage of the schedule has its money beside it.

Try it free for 30 days, no card needed

A schedule only helps if it is kept up to date. Once a week, ideally on site with the builder:

  1. Mark what is finished, checked by you, not just reported.
  2. Mark what is underway, and whether it will finish on time.
  3. Look two weeks ahead: deliveries due, trades booked, decisions needed.
  4. Move dates honestly. If one job slips, move everything that depends on it, not just that one line.
  5. Agree changes to dates in writing, in the same message as any change to the work or price.

Linking the schedule to payments keeps both honest: a stage payment falls due when that stage is finished, not when the calendar says. Our guide to paying a contractor covers how to set those stages.

When the schedule slips

Something will slip. What matters is spotting it early and deciding what to do.

  • Find the cause: a hidden problem, a late decision, a delivery, a trade, the weather.
  • Find the knock-on: which later jobs and deliveries move with it.
  • Decide the response: wait, reorder the work, bring in extra help, or change the scope.
  • Record it: a slip caused by a change you asked for should be on the change record as a variation or extra (change order) agreed in writing; our guide to variations and extras shows what to record.

In the UK (England)

If a trader has not finished on time, Citizens Advice says you have to give them a second chance to finish, unless you made it clear that the work had to be finished by a certain date. It suggests making the new deadline clear and putting it in writing. Its guidance on contracts also suggests agreeing in advance why delays might happen and what the trader will do about them.

A simple renovation schedule, laid out

#JobDepends onWhoDaysOrder byDecide byStatus
1Strip out bathroomSkip bookedBuilder2LayoutDone
2First fix plumbing1, layout agreedPlumber3Shower valveShower positionUnderway
3First fix electrics1Electrician2Light positionsBooked
4Plaster2, 3Plasterer2, then dryingBooked
5Tiling4 dryTiler4Tiles, 3 weeks aheadTiles chosenNot started
6Second fix and fit-out5Plumber, electrician3SanitarywareTapsNot started
7Decorate and snag6Decorator, you3PaintNot started

Illustrative example only. Durations depend on your job; ask your trades.

On the Operation Sicily villa

From the villa in Sicily. The villa renovation that Mekozo's founder, Jonathan Smith, films for Operation Sicily shows how much a schedule is shaped by dependencies. Months two to four went on geometra meetings, permits and preparing the site; months four to eight on cutting and filling wall chases for the electrical ducting, all powered by a generator because there was no mains supply yet. Mains electricity came about ten to twelve months in, and plastering about twenty months in, because every first fix job had to be finished first (The real timeline of a Sicilian villa renovation). Lead times mattered too: the kitchen units were ordered and paid for months ahead, with a three month lead time (Episode 92). And plans moved: when the window fitters were delayed because their transport broke down, he stopped tiling and cleaned up ready for them; the bathroom window was left until the wall tiles were finished, with the fitters coming back in a few weeks (Episode 88). His advice is to plan three or four stages ahead, because each decision commits you further into the future than it seems.

Playing loads YouTube’s external player.

Watch directly on YouTube ↗

Renovation schedule checklist

  • Every job listed room by room, split into separate trade visits
  • Dependencies set for each job
  • Durations from the trades, in working days
  • Buffers for drying, inspections, deliveries and weather
  • Order dates for long lead items
  • Notice periods for neighbours and approvals
  • Decide-by dates for every choice the work depends on
  • A list of open questions and decisions, with owners
  • A weekly review, with dates moved honestly
  • Date changes agreed in writing

For the rest of this stage, see our guide to running the work week by week, how to plan the order of a renovation from the start, and how a snagging list closes the schedule. Mekozo shows jobs as planned, underway and finished, and can keep the records, photos and documents for each job alongside the money; see how to understand estimated, agreed, paid and still to pay.

This guide explains a planning method. Durations and rules vary by job and country; it is not legal or professional advice.

Questions people ask

How do you make a renovation schedule?

List every job room by room, decide what each job depends on, put them in order, and give each one a duration and an owner. Then add order dates for materials with long lead times, dates by which you must make decisions, and buffers for drying, inspections and deliveries. Review it weekly once work starts.

What should a renovation schedule include?

Each line should show the job and where it is, what must be finished first, who does it, how long it takes in working days, the materials and when they must be ordered, and any decision you need to make and by when. Add start and finish dates once the order is set, and a status column once work begins.

How long does a house renovation take?

It depends on the size of the job, the condition of the house, approvals and how many trades are involved. A single room can take weeks; a whole house can take many months. Build your own estimate from the schedule, with buffers, rather than relying on a typical figure, and ask your builder for their programme.

Why do renovations run late?

The common causes are hidden problems found once work starts, late decisions, materials with long lead times ordered too late, trades not available when the previous job finishes, inspections, drying times and bad weather. A schedule that shows dependencies and lead times makes most of these visible early.

What can I do if my builder is running late?

Talk to them first and agree a revised date in writing. In England, Citizens Advice says you usually have to give the trader a second chance to finish, unless you made it clear the work had to be finished by a certain date; it suggests putting the new deadline in writing.

Sources

  1. Citizens Advice, Before you get work done on your home (England) · Checked 18 November 2026
  2. Citizens Advice, Problem with building work, decorating or home improvements (England) · Checked 18 November 2026
  3. GOV.UK, The Party Wall etc Act 1996: explanatory booklet · Checked 18 November 2026
  4. Health and Safety Executive, Are you a domestic client? · Checked 18 November 2026
  5. Operation Sicily, The real timeline of a Sicilian villa renovation · Checked 18 November 2026
  6. Operation Sicily, Episode 88: New windows and doors fitted at my Sicilian villa · Checked 18 November 2026
  7. Operation Sicily, Episode 92: Italian kitchen reveal at my Sicilian villa · Checked 18 November 2026
Jonathan Smith opening the gate of the villa in Sicily

About the author:

Jonathan Smith is the founder of Mekozo and Operation Sicily. Jonathan bought an abandoned villa in Sicily and is rebuilding it on camera, every week. Mekozo is the app Jonathan built to keep that renovation's money in one picture.

Related from Operation SicilyThe real timeline of a Sicilian villa renovation

Real renovation experience and regional guidance from Operation Sicily.

Blog

Related reading

A final bill split into quoted work and extras, with every extra agreed in writing
Renovation work underway

Variations and extras: keep control of the budget

Changes and extras are where renovation budgets drift. What a variation is, the four kinds of change, a five step way to agree each one before the work, and a change log you can copy.

Scaffolding beside an old stone building with tall chimneys
Renovation work underway

Managing a renovation from abroad or at a distance

Renovating a house you cannot visit every day takes a different kind of planning. The local team, written briefs, photo routines, payments and travel costs, with lessons from a villa renovated between the UK and Sicily.

All Blog posts →

Bring the whole picture home.

Budgets, quotes, payments, documents and decisions in one place

30 days free. No card needed.

Monthly, with no annual plan. The Terms of membership set out the details.