How to pay a contractor: payment schedules that work

A good payment schedule keeps your money roughly level with the work done. How to set the deposit, the stages and the final payment, how to pay safely, and what to record each time.

Paying in stages: deposit and stage one paid, stage two and the final payment to come
Contents

Key points

  • Pay a contractor in stages tied to finished work, so the money you have paid never runs far ahead of the work done.
  • Avoid a deposit where you can; Citizens Advice suggests offering to buy materials yourself instead, and not agreeing to more than 25% if a deposit cannot be avoided.
  • Pay by credit or debit card if you can, then bank transfer, and not in cash; card payments can give you a way to get money back.
  • Agree the schedule in writing before work starts, with each stage defined by what will be finished, not by a date.
  • Keep a final payment back until the job is complete, the snagging list is closed and the certificates and guarantees are handed over.

How should you pay a contractor?

Pay a contractor in stages tied to finished work. Keep any deposit small, pay each stage only once that part of the job is done and checked, pay by card or bank transfer rather than cash, and keep a final payment back until the snagging list is closed. Agree the schedule in writing before work starts.

The aim of a payment schedule is simple: your money should stay roughly level with the work done. Pay too far ahead and you carry the risk if the builder disappears or the work goes wrong. Pay too far behind and a good builder ends up funding your job, which is not fair either. This guide shows how to set it up, how to pay safely, and what to record.

How a contractor payment schedule works

Most building jobs are paid in some version of four parts.

PartWhen it is paidWhat it is for
Deposit (if any)Before work startsUsually materials or securing a start date
Stage paymentsAs each defined stage is finishedThe work done in that stage
Payments for changesWhen each agreed change is doneExtras agreed in writing
Final paymentWhen the job is complete and snags are closedThe last part of the work, and the finish line

The amounts depend on the job, but the principle does not: each payment follows work you can see.

In the UK (England)

Citizens Advice says paying in stages is a good idea, because it means problems can be put right before you make the final payment, and suggests being clear about the points in the work when payments are due.

Step 1: keep the deposit small, or avoid it

A deposit is money paid before any work is done. It is the payment most at risk if something goes wrong.

  1. Ask whether a deposit is needed at all. For short jobs it often is not.
  2. If it is for materials, offer to buy them yourself. Citizens Advice suggests this, so you own the materials if something goes wrong.
  3. If it cannot be avoided, keep it low. For a long job, Citizens Advice suggests pushing it down as far as possible and not agreeing to more than 25%.
  4. Get a receipt for the deposit, and for the materials it covers.
  5. Ask how it is protected. Citizens Advice suggests checking whether the trader has insurance to protect your deposit if they go out of business, or uses an escrow scheme registered with the Financial Conduct Authority. The Chartered Trading Standards Institute also explains trusted payment schemes, where the money for a job is committed at the start but released stage by stage as the work is completed and signed off.

Watch out

A request for most of the money upfront, or for cash only, is a warning sign. Citizens Advice suggests avoiding traders who only accept cash or want you to pay everything upfront.

Step 2: define stages by finished work, not dates

A stage payment should be triggered by something you can check, such as "first fix electrics complete", not "week 3". Dates slip; work done is a fact.

Good stages are:

  • Visible: you can see whether it is finished.
  • Checkable: you can look before the walls are closed.
  • Proportionate: the payment roughly matches the value of the work in that stage.

An illustrative stage plan for a bathroom refit:

StageFinished whenShare of price
MaterialsYou have bought them yourself, or a small deposit with receiptUp to 10%
Strip out and first fixOld bathroom out, pipes and cables run, checked before covering25%
Plaster and tilingWalls plastered and tiled, floor laid30%
Fit-out and second fixSanitaryware, taps, lights and fan working25%
CompletionSnagging list closed, certificates and guarantees handed over10%, plus any share not taken as a deposit

Illustrative only. Agree shares that match the value of each stage on your job.

Tip

Take a photo of each stage when it is finished, before you pay. Our guide to renovation before and after photos covers what to record while the walls are open.

Step 3: pay the safe way

How you pay changes what you can do if something goes wrong.

MethodWhat Citizens Advice says
Credit cardPay by card if you can. For a single item costing more than £100 and no more than £30,000, you can ask the card provider for your money back under Section 75 of the Consumer Credit Act
Debit cardYou may be able to get money back through the chargeback scheme if something goes wrong
Bank transferUse if you cannot pay by card. It cannot be claimed through chargeback or Section 75; you might get money back if you were the victim of a scam
CashDo not pay with cash

Sources: Citizens Advice, Before you get work done on your home and Getting your money back if you paid by card.

In the UK

Citizens Advice notes that a Section 75 claim can include a deposit paid by credit card, even if that deposit was less than £100, as long as the item itself fits the price range. It also warns that if you do not pay off a credit card on time, you will usually be charged interest. This is general information, not financial advice.

Watch out

If you receive an email or message saying the builder's bank details have changed, do not pay until you have checked by phone, using a number you already had. If you think you have been scammed after a bank transfer, Citizens Advice explains how to check if you can get your money back.

Step 4: record every payment against the job

Costs & spending in Mekozo, close up: whole project £8,300 plus one unpriced item, paid £2,000, still to pay £3,500, £12,000 in the plan

Mekozo's Costs & spending view shows what is paid so far and what is agreed but still to pay, across every job.

Try it free for 30 days, no card needed

Every payment needs a record that you can find in a minute. For each one, note:

  • The job and stage it pays for
  • The invoice it relates to
  • The amount and the date
  • How you paid, and the reference
  • What is still to pay on that job afterwards

An invoice is the bill for agreed work; record it, then the payment against it. Before paying any invoice, check it against the agreed price and the stage it claims. Our guide to organising renovation receipts and invoices covers the paperwork, and our guide to keeping agreed prices, invoices and payments apart explains why those figures need to stay separate for every job.

Step 5: pay for changes as their own line

Extras are a new commitment, not a quiet change to the old price. Agree each change in writing with its price before it is done, then pay for it as its own line when it is finished. That written agreement is a variation or extra (change order), and our guide to variations and extras shows what to put in it.

That keeps two things separate that otherwise get tangled:

  1. Snags are not a reason to dispute extras. An extra you asked for is owed when it is done.
  2. Extras are not a reason to release money held for snags. The final payment waits for the agreed list to be closed.

Step 6: keep the final payment until the job is truly finished

The final payment is your strongest reason for the builder to come back and finish properly. It should be large enough to matter and small enough to be fair for what is left.

Release it when:

  • Every stage is complete
  • The agreed snagging list is closed, and you have checked each item
  • Agreed changes are priced, done and included
  • Certificates, guarantees and manuals are handed over
  • The final invoice matches the agreed price plus agreed changes, minus what you have paid

Tip

Before the last payment, set three totals side by side: the agreed price plus agreed changes, what you have already paid, and the final invoice. If they do not add up, find out why before any more money goes.

Put the schedule in the contract

Write the payment schedule into the agreement before work starts, so neither side has to remember it.

  • Each stage, what "finished" means for it, and the amount
  • The deposit, if any, what it covers and how it is protected
  • How you will pay
  • How changes are priced and paid
  • What the final payment depends on

Our guide to the home improvement contract covers the rest of what to agree in writing.

In the UK (England)

If a builder asks for more than the quoted price, Citizens Advice explains that a trader cannot charge more than a quote unless there is a good reason, such as extra work you agreed to pay for, and that they cannot charge more just because their own costs have gone up since the quote. Check your paperwork, and put your position in writing.

Signs your payments are running ahead of the work

  • You have paid more than half the price and less than half the work is done.
  • A stage was paid before you could check it.
  • You are being asked for money for materials that have not arrived.
  • Payments are being asked for by date, regardless of progress.
  • Changes are being added to invoices without a written agreement.

If you see these, pause the next payment, talk to the builder, and agree in writing how the schedule will get back in line.

On the Operation Sicily villa

From the villa in Sicily. At the villa Mekozo's founder, Jonathan Smith, is renovating, the kitchen units were ordered and paid for months before they were fitted, because there was a three month lead time, as he shows in Episode 92 of Operation Sicily. For those months the money was committed but the kitchen was not there: exactly the kind of payment that needs a clear record of what was paid, to whom and what is still to come. Even at the reveal, the tap and the sink trap were still to fit, a small finish line before the job was truly complete. In his guide to renovation costs in Sicily, he suggests keeping dates, scope, materials and payment milestones visible so a change in cost can be traced to a change in the job, agreeing payment milestones and how extra work is approved in writing, and treating an informal cash price as no real comparison with a documented offer.

Playing loads YouTube’s external player.

Watch directly on YouTube ↗

Contractor payment checklist

  • Deposit avoided, or kept small, with a receipt and protection checked
  • Materials bought yourself where it makes sense
  • Stages defined by finished, checkable work
  • Each stage paid only after you have checked it
  • Paid by credit or debit card if possible, then bank transfer, never cash
  • Bank detail changes checked by phone before paying
  • Every payment recorded against the job, with date, method and reference
  • Changes agreed in writing and paid as their own lines
  • Final payment held until snags are closed and paperwork handed over
  • The schedule written into the contract before work starts

For the rest of this stage, see our guide to paying and managing builders while work is underway and how to find a good builder before you agree any payments. Our help guide shows how to track agreed, paid and still to pay for every job, and the renovation budget tracker puts it in one place.

This guide explains a practical method for paying for building work. It is not legal or financial advice. Payment protections differ by country and card provider: check the official guidance where you live.

Questions people ask

How much should you pay a builder upfront?

As little as possible. Citizens Advice suggests avoiding deposits or upfront payments where you can, offering to buy materials yourself instead, and if a deposit cannot be avoided on a long job, pushing it down as far as possible and not agreeing to more than 25%. Always get a receipt for it.

What is a fair payment schedule for a contractor?

One where each payment follows a defined stage of finished work, so you are never paying far ahead of what has been done, and the builder is not funding the whole job themselves. A small deposit or materials payment, several stage payments and a final payment after snagging is a common pattern.

Should I pay a builder in cash?

Citizens Advice suggests paying by debit or credit card if you can, then by bank transfer, and not with cash. It says to avoid traders who only accept cash or want everything paid upfront, and notes that cash and bank transfer payments cannot be claimed back through chargeback or Section 75.

Should I pay a builder before the work is finished?

Pay for each stage once it is finished and you have checked it, not before. Keep a final payment back until the whole job is complete, the agreed snagging list is closed, and you have the certificates, guarantees and manuals for the work.

How do I protect my deposit?

Keep it small, pay by credit card if you can, and get a receipt. Citizens Advice suggests checking whether the trader has insurance to protect your deposit if they go out of business, or uses an escrow scheme, and checking that any escrow company is registered with the Financial Conduct Authority.

Sources

  1. Citizens Advice, Before you get work done on your home (England) · Checked 18 November 2026
  2. Citizens Advice, Getting your money back if you paid by card or PayPal · Checked 18 November 2026
  3. Citizens Advice, Check if you can get your money back after a scam · Checked 18 November 2026
  4. Citizens Advice, Problem with building work, decorating or home improvements (England) · Checked 18 November 2026
  5. Chartered Trading Standards Institute, Trusted payments: paying for home improvements · Checked 18 November 2026
  6. Operation Sicily, Episode 92: Italian kitchen reveal at my Sicilian villa · Checked 18 November 2026
  7. Operation Sicily, How much does it really cost to renovate a house in Sicily? (2026) · Checked 18 November 2026
Jonathan Smith opening the gate of the villa in Sicily

About the author:

Jonathan Smith is the founder of Mekozo and Operation Sicily. Jonathan bought an abandoned villa in Sicily and is rebuilding it on camera, every week. Mekozo is the app Jonathan built to keep that renovation's money in one picture.

Related from Operation SicilyHow much does it really cost to renovate a house in Sicily? (2026)

Real renovation experience and regional guidance from Operation Sicily.

Blog

Related reading

A final bill split into quoted work and extras, with every extra agreed in writing
Renovation work underway

Variations and extras: keep control of the budget

Changes and extras are where renovation budgets drift. What a variation is, the four kinds of change, a five step way to agree each one before the work, and a change log you can copy.

All Blog posts →

Bring the whole picture home.

Budgets, quotes, payments, documents and decisions in one place

30 days free. No card needed.

Monthly, with no annual plan. The Terms of membership set out the details.