How to pay a contractor: payment schedules that work
A good payment schedule keeps your money roughly level with the work done. How to set the deposit, the stages and the final payment, how to pay safely, and what to record each time.
Agreed, invoiced, paid and delivered are four different facts. Here is how to track renovation spending so each one stays visible.

To track renovation spending, keep four facts apart for every job and purchase: what you agreed to pay, what has been invoiced, what you have paid and, for goods, delivery. Each moves on its own timeline. A good way of tracking costs gives each job a line and shows the number that matters most: what is still to pay.
This guide shows you the stages to track, how to set up a tracker, and the checks to run each week while work is underway.
When building work starts, most people watch their bank balance. The trouble is that money paid is only part of the story. By the middle of a project you have usually agreed to far more than you have paid: the builder's contract, a kitchen on order, a deposit on windows, and changes agreed on site.
| You see | What it misses |
|---|---|
| £18,000 paid | £41,000 agreed in contracts and orders |
| Kitchen deposit paid | The balance due on delivery |
| An invoice for this week | Two changes agreed verbally, not yet invoiced |
| Nothing paid for the rewire | The rewire has no price yet |
The number that tells you whether the budget still works is the committed total, plus anything still unpriced. "Spent so far" is just the part of it that has already happened.
Every cost passes through stages. Track each one separately.
Invoices sit alongside these stages. An invoice is the bill for agreed work; record it, then the payment against it. Work with no price yet is not zero: until it is priced, your real total is higher than any figure on the page.
Watch out
An invoice is not the same as a payment, and a payment is not the same as completed work. Pay against what has been done, not against the invoice alone.
Goods add a fourth fact: whether they have arrived. Ordering a kitchen, paying for it and receiving it can happen months apart.
| Fact | Question it answers |
|---|---|
| Ordered | Have we committed, and to what specification? |
| Paid | How much has left our account, and how much is due on delivery? |
| Delivered | Has it arrived, complete and undamaged? |
| Fitted | Is it installed and working? |
Treating these as one event makes it harder to understand both your cash and your progress. A kitchen marked "paid" might be weeks from delivery; a tile order marked "delivered" might still have a balance to pay.
In the UK
Citizens Advice says that if you buy something from a business to be delivered, it is the seller's responsibility to make sure it arrives, and explains when you can ask for a full refund: if an essential delivery date was missed, if an agreed date and a second date were both missed, or if no date was agreed and a second chance to deliver also failed. Keep the order confirmation and the agreed date with the purchase so you can show it.

Mekozo's Costs & spending view keeps the whole project so far, what is paid and what is agreed but still to pay as separate totals, and flags work with no price yet.
Try it free for 30 days, no card neededYou can do this in a spreadsheet or an app. The method is what matters.
A simple tracker looks like this:
| Area | Item | Agreed price | Invoiced | Paid | Still to pay | Status |
|---|---|---|---|---|---|---|
| Kitchen | Units and worktops | £9,400 | £4,700 | £4,700 | £4,700 | Ordered, due in 6 weeks |
| Kitchen | Fitting | £2,200 | £0 | £0 | £2,200 | Not started |
| Bathroom | Builder stages 1 to 3 | £7,800 | £5,200 | £5,200 | £2,600 | Stage 3 in progress |
| Bathroom | Extra: move radiator | £350 | £0 | £0 | £350 | Agreed on site, confirm in writing |
| Whole house | Rewire | No price yet | Unknown | Quote awaited | ||
| Total | £19,750 + rewire | £9,900 | £9,900 | £9,850 + rewire |
Illustrative figures only.
Tip
Keep receipts and invoices with the line they belong to. When a supplier queries a payment or something is missing, you can check the order, delivery and payment records in one place before you chase.
How you pay affects how well your tracker protects you.
Agree a payment schedule tied to stages you can check before work starts, as our guide to how to pay a contractor explains.
Ten minutes once a week keeps the tracker honest.
Changes deserve special care. RICS warns that changes after work starts are usually very expensive. Each one is a variation or extra (change order), and our guide to variations and extras explains how to price it before you agree, and our guide to renovation contingency shows how to keep track of what is left.
On the Operation Sicily villa
From the villa in Sicily. The kitchen at the villa Mekozo's founder, Jonathan Smith, is renovating shows why ordered, paid and delivered are different facts. He ordered and paid for the units months before they could be fitted, because there was a three month lead time. On the day, the kitchen arrived by van and was unloaded on a hand trolley, with the appliances still in their boxes, as he shows in Episode 92 of Operation Sicily, where he films the renovation. For those months, the money was gone but the kitchen was not there. Smaller purchases need the same care: early in the project he bought a 3000 watt generator for about €350 at a DIY store in Palermo (Episode 14), the kind of cost that slips out of a budget if it is not recorded the day it is paid. You can follow the work as it happens in his renovation deep dives.
Playing loads YouTube’s external player.
Watch directly on YouTube ↗Before the final payment:
For more on this stage, see our guide to keeping costs and builders on track. Your next step is the renovation budget tracker, which keeps agreed, paid and still to pay in view, and our help guide explains how to understand estimated, agreed, paid and still to pay in Mekozo.
This guide explains a method for tracking building costs. It is not legal or financial advice; payment protections differ by country, so check the official guidance where you live.
Give every job and purchase its own line, and record each stage separately: the estimate, the agreed price, what has been invoiced and what has been paid. For purchases, add the order and delivery status. Still to pay is the agreed price minus what you have paid, and it is the figure that tells you what you can still afford.
Committed is everything you have agreed to pay, through accepted quotes and orders. Spent is what has already left your account. On a project underway, committed is usually much bigger than spent, and it is the committed figure that tells you whether the budget still works.
For each line: the room or area, the supplier or trade, the agreed price, invoices received, payments made with dates and method, what is still to pay, and for goods the order and delivery dates. Keep the quote, invoices and receipts with the line they belong to.
Citizens Advice suggests paying for building work by debit or credit card if you can, then bank transfer, and not with cash. Paying by card can give you a way to get money back if something goes wrong; it notes that cash and bank transfer cannot be claimed through chargeback or section 75.
Check your order, the agreed delivery date and your payment record first, then contact the seller. Citizens Advice says it is the seller's responsibility to make sure the item is delivered, and explains when you can ask for a full refund if an agreed or essential delivery date is missed.
Real renovation experience and regional guidance from Operation Sicily.

A good payment schedule keeps your money roughly level with the work done. How to set the deposit, the stages and the final payment, how to pay safely, and what to record each time.

A simple system for renovation paperwork: capture every receipt and invoice the day it arrives, file it against the job it belongs to, check it, and keep what you will need later.

Changes and extras are where renovation budgets drift. What a variation is, the four kinds of change, a five step way to agree each one before the work, and a change log you can copy.