How much renovation contingency should you allow?

Size your renovation contingency from the real unknowns in your project, keep upgrades out of it, and watch what is left after every change.

A budget split into planned work and a contingency kept apart for surprises
Contents

Key points

  • Most UK guides suggest a renovation contingency of 10% to 15% of the build cost: Which? advises around 10% to 15%, and the Federation of Master Builders suggests 15% or more for older homes or structural work.
  • Treat the percentage as a starting point, then size the contingency from the genuine unknowns in your own project.
  • List each unknown, such as what is behind walls, under floors and in the roof, put a low and high figure on it, and decide how much of that risk to cover.
  • A contingency is for things you could not know, not for upgrades you choose along the way.
  • Check what is left in the contingency every time you agree a change or find new work.

Most UK guides suggest a renovation contingency of 10% to 15% of the build cost, and more for an older house: Which? advises around 10% to 15%, and the Federation of Master Builders suggests 15% or more for older homes or structural work. Treat that as the starting point, then check it against your own project's unknowns.

A percentage on its own tells you nothing about your house, so list the genuine unknowns, such as what is behind the walls, under the floors and in the roof, which items are only allowances and which prices are not fixed, and cover those. Keep upgrades out of it, and recheck it after every change. This guide shows you how to size, protect and track a contingency that has a clear job to do.

What a renovation contingency is, and what it is not

A contingency is money you hold back for costs you cannot know yet. It is not a second budget for things you would like.

Belongs in contingencyDoes not belong in contingency
Rot, damp or structural problems found when opening upAn upgrade to a better kitchen worktop
Old wiring or pipework that must be replaced once exposedThe extra room you already know you want
Items priced only as allowances or provisional sumsA change of mind about the tile you chose
Price rises on materials not yet orderedFurniture and decoration after the build
Delays that add to rent or living costsAnything already in the scope with a price

Tip

If you already know you want something, put it in the scope and the budget with its own price. Calling it contingency does not make it cost less, it just hides it.

Why renovation costs move once work starts

Three forces push costs up during a project, and a contingency is there to absorb them.

Hidden conditions

Some problems only appear when walls, floors and roofs are opened. A survey reduces the unknowns but cannot remove them. RICS notes that its most thorough survey, the Level 3 Home Survey, is the one to choose for large, older or run-down properties or if you are planning major works.

Changes after work begins

RICS's consumer guide to home extensions and improvements warns that changes made after work starts are usually very expensive, and recommends agreeing a method for making changes before work begins.

Prices that are not fixed

Under a quote, Citizens Advice says the price can only go up if you ask for extra work, agree to extra work the trader tells you about, or there was a genuine mistake (Before you get work done on your home). Anything that is only an estimate, a daily rate or an allowance can move. And material prices change: the UK government's construction building materials commentary, published 4 November 2026, showed the material price index for all work up 7.2%, and for repair and maintenance up 6.2%, between September 2025 and September 2026.

How to size your renovation contingency, step by step

Step 1: list the genuine unknowns

Walk through the project and write down every cost you cannot yet pin down. Group them:

  • Hidden conditions: areas not yet opened, such as under floors, behind plaster, in the roof, below ground.
  • Open decisions: items where you have not chosen the specification, so the price is a guess.
  • Allowances: items in the quote marked as provisional sums or "allow for".
  • Unfixed prices: estimates, day rates and materials not yet ordered.
  • Time: what a delay would cost you in rent, travel or a second home.

Watch out

Open decisions are not contingency. They need a decision, not a fund. Make the decision, price it, and move it into the budget. What remains on the list is genuine uncertainty.

Step 2: put a range on each one

For each unknown, write a low and a high figure. Ask your builder or surveyor where you can: "If the joists under the bathroom are rotten, what would replacing them cost?" A rough range is far more useful than a blank.

Step 3: decide how much of the risk to cover

You do not need to cover every worst case at once; they will not all happen. A practical approach:

  1. Cover in full anything that would stop the job or make the house unsafe if it happened, such as structure, roof, drainage and electrics.
  2. Cover part of the rest, more for older houses and less where quotes are fixed.
  3. Add the cost of a realistic delay.

The total is your contingency. You can sense-check it as a share of the build cost, but the list is what tells you whether it is enough.

RiskLowHighCover
Floor joists under bathroom£0£1,500£1,500 (structural)
Rewire beyond quote if old cable found£0£2,000£2,000 (safety)
Plaster failing when tiles removed£200£900£600
Tile allowance overspend£0£600£300
Four weeks' delay, extra rent£0£1,200£600
Contingency£5,000

Illustrative figures only. Use your own builder's and surveyor's figures.

Step 4: track what is left after every change

Costs & spending in Mekozo, close up: whole project £8,300 plus one unpriced item, paid £2,000, still to pay £3,500, £12,000 in the plan

Mekozo's Costs & spending view shows the whole project so far against the money in your plan, so you can see how much room is left after every new commitment.

Try it free for 30 days, no card needed

The useful question is not whether the contingency looked comfortable at the start. It is how much flexibility remains after the latest commitment.

  • Keep the contingency as its own line, never mixed into the build cost.
  • When an unknown becomes a real cost, move the money out of contingency into an agreed cost, with a note saying why.
  • Cross the risk off the list once it has passed, for example once the floor is open and found sound.
  • Before agreeing any extra, check the contingency left after everything already committed.

Our renovation budget tracker explains how to keep estimates, agreed prices and payments apart so this stays visible.

How the risks change from one project to another

The same list method works for any job, but the kinds of risk differ. Use this as a prompt when you write your own list. Our line-by-line kitchen renovation budget shows where those unknowns sit in a single room.

Type of projectWhere the unknowns usually sitWhat reduces them
Decorating and cosmetic work in a newer homePlaster and surfaces once old finishes come offFixed quotes, a sample area stripped first
A new kitchen or bathroomPipes, drains, wiring and floors behind and below the old fittingsLifting a floorboard or panel before quotes, a clear scope
An older house being opened upStructure, damp, roof timbers, old wiring and drainageA Level 3 survey, specialist checks, opening up the riskiest areas first
An extension or loftGround conditions, structure, connections to the existing house, permissionsFull design, structural input, fixed prices for the main package
A project managed from a distanceDelays, decisions waiting for your next visit, travelClear decision rules, someone trusted on site, a time allowance

Watch out

A common mistake is to set a contingency once and never look at it again. The project changes every week; the list of risks should too. Another is to borrow from it for a nicer finish early on, then have nothing left when the floor comes up.

How to protect your contingency

  • Do not spend it on upgrades. If you want to upgrade, fund it from savings in another line, or decide to reduce the risk cover knowingly.
  • Price changes before agreeing them. RICS advises agreeing in advance how changes will be made and what their time and cost implications will be. Agree each variation or extra (change order) in writing, with its price and its effect on the timetable, before the work goes ahead, as our guide to variations and extras explains.
  • Reduce the unknowns early. Open up the riskiest areas first where it is safe to do so, so you learn the worst early while you still have choices.
  • Release it late. Keep the contingency until the risks it covers have passed.

In the UK

Citizens Advice suggests paying for building work in stages, so problems can be put right before the final payment, and RICS suggests holding back 5% of the price until the work is satisfactorily complete. Neither is contingency, but both protect your budget at the end of the job.

On the Operation Sicily villa

From the villa in Sicily. Early in the villa project, Jonathan Smith, Mekozo's founder, who films his villa renovation on Operation Sicily, broke his budget into labour, materials, and permits and fees, then set aside a backup fund of 10 to 15% on top so surprises would not derail the main priorities (Episode 14). As the work went on, concealed drainage, electrical back boxes that had been plastered over and forgotten, and roof sections that looked sound but were not all needed unplanned spending. In his later renovation cost guide, he writes that on an abandoned property he would now hold back 20 to 25% of the build cost. One risk shows why a list beats a percentage: a single cesspit test decided whether the system could stay or would need replacing at a cost that could have gone upwards of €12,000. It passed (Episode 57).

Playing loads YouTube’s external player.

Watch directly on YouTube ↗

Your next step

Write down the uncertainties your contingency is meant to cover, with a low and high figure for each. Revisit the list whenever you accept a quote or discover new work. For the wider budget, see our guides to setting a home renovation budget and renovating an old house, how to compare builders' quotes, our guide to budgeting and planning a renovation before work starts, and how to build a whole-project budget in Mekozo, with the contingency as its own line.

This guide explains a budgeting method. It is not financial advice; size your contingency from your own survey, quotes and risks.

Questions people ask

How much contingency should I allow for a renovation?

Most UK guides suggest 10% to 15% of the build cost: Which? advises setting aside around 10% to 15% for contingencies, and the Federation of Master Builders suggests 15% or more for older homes or structural work. Then check it against the risks in your own project: the age and condition of the house, how much has been surveyed, how many decisions are still open and how long prices are fixed for. A newer house with fixed quotes needs less; an old house with hidden areas and open decisions needs more.

What should a renovation contingency cover?

It should cover genuine unknowns: hidden conditions found when walls, floors or roofs are opened, items that could only be priced as allowances, and price changes on anything not yet fixed. It should not cover upgrades or extras you already know you want; those belong in the scope and budget.

Is contingency included in a builder's quote?

Usually not as a separate fund for you. A quote may contain provisional sums for items that cannot be priced yet, but your contingency is money you hold back yourself for things outside the quote. Keep the two apart so you can see how much flexibility remains.

What happens to unused contingency?

If the risks it was set aside for have passed, the money is still yours. Release it only once the work it was protecting is finished, such as after the roof is open and repaired, rather than spending it early on upgrades.

Why do renovation costs go up during a project?

Common reasons are hidden problems found once work starts, changes made after work begins, items that were only estimates or allowances, and material prices rising. UK government statistics showed the material price index for all construction work up 7.2% in the year to September 2026.

Is 10% contingency enough for a renovation?

It can be for a simple job with fixed quotes and few hidden areas, but a percentage is a guess about your house, not a measure of it. List the genuine unknowns, put a low and high figure on each, and compare the total with your 10%. If the list is bigger, the percentage is too small.

Sources

  1. Which?, Extension costs (contingency of around 10% to 15%) · Checked 18 November 2026
  2. Federation of Master Builders, How to keep your renovation on budget · Checked 18 November 2026
  3. Department for Business and Trade, Construction building materials: commentary October 2026 · Published 4 November 2026
  4. RICS, Home extensions and improvements consumer guide · Published 8 April 2022, checked 18 November 2026
  5. Citizens Advice, Before you get work done on your home (England) · Checked 18 November 2026
  6. RICS, House surveys: the costs, types and benefits of an RICS Home Survey · Checked 18 November 2026
  7. Operation Sicily, Episode 14: How to budget for a renovation in Italy · Checked 18 November 2026
  8. Operation Sicily, Episode 57: Testing a cesspit soakaway system · Checked 18 November 2026
  9. Operation Sicily, How much does it really cost to renovate a house in Sicily (2026) · Checked 18 November 2026
Jonathan Smith opening the gate of the villa in Sicily

About the author:

Jonathan Smith is the founder of Mekozo and Operation Sicily. Jonathan bought an abandoned villa in Sicily and is rebuilding it on camera, every week. Mekozo is the app Jonathan built to keep that renovation's money in one picture.

Related from Operation SicilyEpisode 14: How to budget for a renovation in Italy

Real renovation experience and regional guidance from Operation Sicily.

Blog

Related reading

A renovation budget by room: kitchen, bathroom, rewiring and one job not priced yet
Planning a renovation

Home renovation budget: how to set one, step by step

A home renovation budget is a spending limit, a scope and a list of every cost, with a contingency on top. Eight steps to set one, the lines people miss, and how to keep it honest once work starts.

A builder repairing an old brick wall by hand
Planning a renovation

Renovating an old house: what to check and budget for first

An old house rewards patience. Check the structure, roof, damp, services and paperwork before you plan finishes, do the work in the right order, use materials that suit how the house was built and give the unknowns their own budget.

A final bill split into quoted work and extras, with every extra agreed in writing
Renovation work underway

Variations and extras: keep control of the budget

Changes and extras are where renovation budgets drift. What a variation is, the four kinds of change, a five step way to agree each one before the work, and a change log you can copy.

All Blog posts →

Bring the whole picture home.

Budgets, quotes, payments, documents and decisions in one place

30 days free. No card needed.

Monthly, with no annual plan. The Terms of membership set out the details.