Planning a renovation

Scope of works: what to include, with an example

What a scope of works should include, what each section should say, and a worked example that builders can price like for like.

A renovation scope: kitchen and rewiring now, loft and garden later
Contents

Key points

  • A scope of works is the written description of the job you want a builder to price: what is included, what is not, the materials and finishes, and what finished looks like.
  • List the work room by room with numbered items, name the materials, state the exclusions and flag every decision still to make.
  • Send the same scope to every builder so their quotes describe the same job.
  • Without a scope, each builder prices the job they imagine, which is why quotes for the same room can be far apart.
  • Keep the scope up to date through the job: date each new version when a change is agreed.

A scope of works is the written description of the job you want a builder to price: what is included, what is not, the materials and finishes, and what finished looks like. List the work room by room, name the materials, state the exclusions and flag open decisions. Then send the same document to every builder.

Without a scope, each builder quotes for the job they imagine. That is why two quotes for "a new bathroom" can be far apart and still both be reasonable.

Why a scope of works matters

A scope of works does three jobs at once.

  • It gets you comparable quotes. RICS's consumer guide to home extensions and improvements says a major extension should be fully designed to help builders give comparable quotes, and recommends a fully itemised and costed schedule of works confirmed in writing.
  • It protects your budget. Every gap in the scope is a possible extra later. RICS warns that changes made after work starts are usually very expensive.
  • It becomes part of the contract. Citizens Advice recommends a written contract that sets out exactly what you are paying for, and says it can refer back to the quote for this (Before you get work done on your home). A clear scope makes that quote clear.

Start with the outcome, not the solution

Before listing tasks, write down what the work must achieve. "A kitchen we can cook in together", "a bathroom that does not get mouldy" and "a warm loft room for a teenager" are outcomes. They help you, and the builder, judge whether a proposed solution actually solves the problem.

Then walk the house and follow the connections. Changing one room often touches others:

  • A new kitchen may need new electrics, plumbing, ventilation and flooring.
  • Moving a bathroom may need new drainage runs and a check on the floor structure.
  • A loft room needs stairs, fire safety, insulation and possibly structural work.

Write each knock-on job into the scope, or into a list of open questions if you do not know the answer yet.

What to include in a scope of works

SectionWhat it should say
1. Project detailsAddress, your contact details, who is writing the scope, date and version
2. The outcomeWhat the finished work must achieve, in one or two sentences per area
3. Existing conditionWhat is there now, known problems, survey findings, photos
4. The work, by room or areaEach task in plain words: strip out, build, install, make good, finish
5. Materials and finishesBrand, range or standard for each item, or "builder to propose"
6. Who supplies whatItems you will buy, items the builder supplies, and who fits them
7. ExclusionsWhat is not in this job, stated plainly
8. Permissions and certificatesPlanning, building regulations, party wall, certificates you expect at the end
9. Site rulesWorking hours, access, parking, toilet, waste and skips, protection of other rooms
10. ProgrammePreferred start date, any fixed deadlines, phasing if you live in during work
11. PaymentsHow you want to pay: stages, retention, how extras will be agreed
12. Open questionsEverything still undecided, with who needs to decide it

Tip

Number every item. When quotes come back, you can ask each builder to price against the same numbers, which makes the comparison far quicker.

A scope of works, section by section

Use this outline as the order for your own scope, and leave out anything that does not apply.

1. Project details

  • Property address:
  • Owner and contact:
  • Scope written by:
  • Date and version:

2. Outcome

  • [Area]: what the work must achieve

3. Existing condition

  • What is there now:
  • Known issues and survey findings:
  • Photos attached: yes / no

4. Work, by area

  • 4.1 [Area] Strip out:
  • 4.2 [Area] Structural or first fix:
  • 4.3 [Area] Second fix and finishes:
  • 4.4 [Area] Making good and decoration:

5. Materials and finishes

  • [Item]: specified / allowance of £___ / builder to propose

6. Supply

  • Client supplies:
  • Builder supplies:

7. Exclusions

  • Not included:

8. Permissions and certificates

  • Planning permission needed: yes / no / to check
  • Building regulations approval or competent person certificate: yes / no / to check
  • Certificates expected at handover:

9. Site rules

  • Working hours, access, parking, welfare, waste, protection:

10. Programme

  • Earliest start, fixed dates, phasing:

11. Payments and changes

  • Proposed stages, retention, how changes will be priced and agreed in writing:

12. Open questions

  • Question, who decides, by when:

Worked example: a family bathroom

Here is how one area looks when filled in. It is an illustration of the level of detail, not a recommended specification. Our bathroom renovation budget shows how to price the same lines.

No.ItemDetail
4.1Strip outRemove bath, basin, WC, tiles and flooring. Remove waste from site. Protect landing carpet.
4.2First fixMove WC waste 600 mm to the window wall. New supply pipes to shower. Install extractor fan ducted to outside. New lighting circuit with two downlights.
4.3Walls and floorBoard walls in the shower area with tile backer board. Level the floor.
4.4FitFit client-supplied shower tray, glass screen, basin and WC. Builder supplies valves and fittings to match.
4.5TilingFloor-to-ceiling tiles in shower area, half height elsewhere. Tiles client-supplied; builder supplies adhesive, grout and trims.
4.6FinishSeal all joints, fit accessories, decorate ceiling and walls not tiled.
5MaterialsShower valve: thermostatic, builder to propose two options with prices.
7ExclusionsHeated towel rail (separate decision). Landing redecoration.
8CertificatesElectrical work to be certified; certificate handed over at completion.
12Open questionsIs the floor under the old bath sound? Builder to inspect after strip out and price any repair separately before proceeding.

Notice what this does. Two builders reading it will price the same tray position, the same tiling height and the same extractor fan. The one genuine unknown, the floor under the bath, is named, and there is an agreed way to deal with it.

Watch out

"allow for" and "as required" are the two most expensive phrases in a scope. If you cannot specify an item yet, give it a clear allowance (for example "tiles: allowance of £30 per square metre, client to choose") so every quote uses the same figure.

Permissions and certificates to put in the scope

Some work needs permission before it starts, and some needs certificates when it ends. Put both in the scope so they are priced and nobody assumes the other is handling them.

In the UK (England and Wales)

Citizens Advice says you usually need planning permission to build something new, make a major change to an existing building such as an extension, or change a building's use, and points to GOV.UK's planning permission guide to check. Separately, most plumbing, electrical and heating work and anything affecting energy efficiency falls under building regulations. GOV.UK says you do not need to get building regulations approval yourself if you use someone registered with a competent person scheme, and warns that without approval you will not have the certificates you may need when you sell. Other parts of the UK, and other countries, have their own systems.

How to turn your scope into quotes you can compare

Two quotes for the same kitchen in Mekozo, close up: £5,500 accepted and £6,200 received, each with what it includes and excludes

Mekozo lines up the quotes that come back on your scope side by side, with what each includes and excludes and its timing, and it turns your scope into a scope of works PDF you can send to every builder.

Try it free for 30 days, no card needed
  1. Send the same scope to every builder. Same version, same numbering.
  2. Ask for prices against your item numbers. Not one lump sum.
  3. Ask each builder what they would change. Good builders often spot something you missed; add it to the scope and send the update to everyone.
  4. Record exclusions and assumptions. Anything a builder leaves out goes on a list for that quote.
  5. Price the open questions separately. So an unknown does not quietly inflate one quote and not another.

Citizens Advice suggests getting written quotes from at least three traders, and RICS suggests at least three detailed quotes. Our guide to what a good builder quote includes shows how to compare them line by line.

On the Operation Sicily villa

From the villa in Sicily. When Mekozo's founder, Jonathan Smith, needed plastering quotes for his villa, he sprayed green crosses on every wall and ceiling he wanted skimmed, so the plasterers could see exactly what to price, as he shows in Episode 29 of Operation Sicily, where he films the renovation. The scope was on the walls themselves. Earlier, his planning paperwork shaped the scope too: one SCIA notification, filed through a geometra, covered an outbuilding for the well pumps, a staircase to the roof terrace, a patio, new windows and the electrical work. He then asked electricians to quote for a complete rewire, air conditioning, a new consumer unit and the supply for a pool, garden lighting and the rear patio (Episode 11). Listing every item up front is what makes quotes from different trades comparable. His practical guide to renovating a house in Sicily covers the Italian permissions in detail.

Playing loads YouTube’s external player.

Watch directly on YouTube ↗

Keep the scope alive

A scope is not finished when the builder starts. Keep it as the reference for the whole job.

  • When you agree a change, update the scope and date the new version. Each change is a variation or extra (change order), and our guide to variations and extras shows how to price and record it.
  • When an open question is answered, move it into the work list with its price.
  • When the job is done, check each numbered item off before the final payment.

For where scoping sits in the wider plan, see our home renovation checklist, our guide to setting a home renovation budget, and our guide to planning a renovation, from the first idea to the quotes. When you are ready to put prices against your scope, the renovation budget tracker shows how to keep estimates, quotes and agreed prices apart. Your first step in Mekozo: set up your first project and write the scope against it.

This guide explains how to describe building work so it can be priced. It is not legal or professional advice; for structural, gas or electrical work, use qualified professionals.

Questions people ask

What is a scope of works?

A scope of works is a written description of the building work you want done: what is included, what is not, the standard of materials and finishes, and what finished looks like. It is what builders price from, so a clear scope is the first step to quotes you can compare.

What should a scope of works include?

It should include the project and property details, the outcome you want, the work room by room or trade by trade, the materials and finishes, what is excluded, who supplies what, permissions and certificates, site rules, and a list of open questions. Each item should be specific enough that two builders would price the same thing.

Who writes the scope of works for a home renovation?

On a small job, homeowners often write it themselves and refine it with the builders who quote. On larger or structural work, an architect, surveyor or designer usually prepares drawings and a specification. RICS recommends that major extensions are fully designed so builders can give comparable quotes.

Is a scope of works the same as a schedule of works?

They overlap. A scope of works describes what will be done and to what standard; a schedule of works usually breaks that into itemised tasks, often with quantities and prices. Many homeowners combine them into one document, which is fine as long as it is specific.

How detailed should a scope of works be?

Detailed enough that two builders reading it would price the same job. If an item could be done in a cheap way and an expensive way, say which you want or mark it as a choice still to make. Vague items are where quotes drift apart and extras appear later.

Sources

  1. RICS, Home extensions and improvements consumer guide · Published 8 April 2022, checked 18 November 2026
  2. Citizens Advice, Before you get work done on your home (England) · Checked 18 November 2026
  3. GOV.UK, Planning permission: when you need it · Page updated 20 October 2026, checked 18 November 2026
  4. GOV.UK, Building regulations approval · Page updated 20 October 2026, checked 18 November 2026
  5. Operation Sicily, Episode 29: Marking walls for plaster quotes and reusing old drains · Checked 18 November 2026
  6. Operation Sicily, Episode 11: Italian building amnesty and my villa · Checked 18 November 2026
Jonathan Smith opening the gate of the villa in Sicily

About the author:

Jonathan Smith is the founder of Mekozo and Operation Sicily. Jonathan bought an abandoned villa in Sicily and is rebuilding it on camera, every week. Mekozo is the app Jonathan built to keep that renovation's money in one picture.

Related from Operation SicilyRenovating a house in Sicily: my practical guide

Real renovation experience and regional guidance from Operation Sicily.

Blog

Related reading

Plan a renovation in order: scope, quotes, budget and schedule
Planning a renovation

Home renovation checklist: plan it in the right order

A renovation goes better when the decisions come in the right order. A phase-by-phase checklist from first idea to handover: what to decide, what to check, who to book and what order the work goes in, with the sources behind each step.

A final bill split into quoted work and extras, with every extra agreed in writing
Renovation work underway

Variations and extras: keep control of the budget

Changes and extras are where renovation budgets drift. What a variation is, the four kinds of change, a five step way to agree each one before the work, and a change log you can copy.

All Blog posts →