
How to pay a contractor: payment schedules that work
A good payment schedule keeps your money roughly level with the work done. How to set the deposit, the stages and the final payment, how to pay safely, and what to record each time.
A snagging list (a punch list) records every defect left at the end of a job. How to write one room by room, agree it with your builder and close it before the last payment.

A snagging list is a written list of every defect and unfinished item left when building work is "finished": a chipped tile, a door that sticks, a gap in the sealant. Walk the job room by room, write each problem as one line with a photo, agree it with your builder, and pay the final amount once it is closed.
In the US and Canada the same document is called a punch list.
This guide shows you what to check, how to write each item so it actually gets fixed, and how to tie the list to your last payment.
A snagging list does three jobs:
It is not a list of new ideas. If you decide you now want an extra socket or a different tile, that is a change, not a snag, and it needs its own price, as our guide to variations and extras explains.
| Snag (builder fixes it) | Change (you agree a new price) |
|---|---|
| Tile cracked during fitting | Swapping to a different tile |
| Door rubs on the new floor | Adding a door that was not in the scope |
| Sealant missing round the bath | Upgrading the bath |
| Socket not working | An extra socket added after the job was priced |
Do it when the builder tells you the work is complete, before you make the final payment, and ideally before you fill the rooms with furniture.
In the UK (new-build homes in England)
The New Homes Quality Code gives buyers the opportunity of a pre-completion inspection, and the New Homes Quality Board publishes a standard checklist for it (Version 2, March 2026). It says internal walls, ceilings, paintwork and sealant should be inspected in daylight from at least 2 metres away without shining a light on the surface, and kitchen and bathroom units and fitted furniture from 0.5 metres. If you find problems in the first two years after moving in, Which? explains that you contact your builder to get them fixed, and that the New Homes Ombudsman Service can order remedial work or compensation if a registered developer does not resolve them.
Tip
Inspecting from a fixed distance is fairer to both sides. Almost any wall shows something with a torch held flat against it; the question is whether it looks right at normal viewing distance.
Work in the same order in every room: ceiling, walls, windows, doors, floor, fittings, services. Use this as the basis of your snagging list.
Watch out
Some items cannot be judged by looking. If work needed building regulations approval, such as a new bathroom involving plumbing, electrics near a bath or shower, or replacement windows (GOV.UK), ask for the completion certificate or the competent person scheme certificate as an item on the list. GOV.UK notes that without approval you will not have the certificates you may need when you sell.
A good snag line answers five questions: where, what, who, by when and done or not.
| # | Room and exact spot | Problem | Photo | Trade | Fix by | Status |
|---|---|---|---|---|---|---|
| 1 | Bathroom, behind basin tap, left | Grout missing | Yes | Tiler | 12 Dec | Open |
| 2 | Kitchen, drawer under hob | Front sits 3 mm proud of the next | Yes | Kitchen fitter | 12 Dec | Open |
| 3 | Bedroom 2, door | Catches on new floor when closing | Yes | Carpenter | 12 Dec | Fixed, checked |
| 4 | Landing | Paint splash on light switch | Yes | Decorator | 12 Dec | Open |
Rules that keep the list useful:
Paper and a camera are enough for a one-room job. On a bigger job, with several trades and dozens of items, a snagging app or a shared spreadsheet keeps the list in one place. Whatever you use, it should do these jobs:
Tip
Test whatever you choose on one room before the real inspection. If adding an item with a photo takes more than a few seconds, you will stop doing it halfway round the house.
Mekozo is not a dedicated snagging app, but it covers the jobs around the list: photos by room, contractors and their quotes, progress tracking, expenses and payments, and handover records, all in one project.

Mekozo's Property Record keeps each finished job with its room, what it cost, what is paid and the documents connected to it, so the handover paperwork is in one place.
Try it free for 30 days, no card neededWalk the list with the builder or site manager, item by item. Expect some discussion: a few items may turn out to be normal for the material, and a few may be changes rather than snags. Settle each one there and then.
In the UK (England)
If a trader does not fix a problem, Citizens Advice says they should fix it within a reasonable amount of time without causing you too much inconvenience. The law does not say what reasonable means, so you agree it between you. If they cannot or will not fix it, you can ask for a partial or full refund depending on how serious the problem is, and once you have agreed an amount, the refund should come within 14 days. Rules differ in Scotland, Wales and Northern Ireland, and in other countries.
The snagging list is what makes the last payment fair to both sides. The builder knows exactly what stands between them and being paid; you know exactly what you are paying for.
Tip
Before you pay, set the totals side by side: the agreed price plus agreed changes, what you have already paid, and what is left. If those three do not add up, find out why before any more money goes.
An invoice is the bill for agreed work; record it, then the payment against it. Our guide to keeping agreed prices, invoices and payments apart explains how as the job goes on.
On the Operation Sicily villa
From the villa in Sicily. When the kitchen was fitted at the villa Mekozo's founder, Jonathan Smith, is renovating, the reveal was not quite the end: the tap still needed fitting and the trap under the sink had to go on, as he shows in Episode 92 of Operation Sicily. Two small jobs, but exactly the kind of items that belong on a written list so they do not drift. The window installation worked the same way: every window and door went in except the bathroom window, which had to wait for the wall tiles, with the installers coming back in a few weeks to fit it (Episode 88). Some checks also have to happen before the finish hides them. Jonathan flushed the new bathroom pipework and held it under pressure before filling the chases with mortar (Episode 79). His practical guide to renovating a house in Sicily covers how each stage is approached.
Playing loads YouTube’s external player.
Watch directly on YouTube ↗For everything else while the work is on site, see our guide to finishing and handing over building work, how to keep the agreed price, invoices and payments apart, and how to plan stage payments that keep you in control. To see how Mekozo keeps the budget and the open items together, look at the renovation budget tracker, and see how to understand estimated, agreed, paid and still to pay.
This guide explains a practical method. It is not legal advice; for a dispute, check the rules where you live and speak to an adviser.
A snagging list is a written list of defects and unfinished items found at the end of building work, such as cracked tiles, missing sealant or a door that sticks. In the US and Canada it is called a punch list. Each item names the room, the problem, who will fix it and by when, so you and the builder are working from the same list.
Do it when the builder says the work is finished and before you make the final payment. Inspect in daylight, with the rooms empty and clean, so marks and gaps are easy to see. For a new-build home in England, the New Homes Quality Code gives buyers the opportunity of a pre-completion inspection.
Check walls and ceilings, paintwork, floors, doors and windows, kitchen and bathroom fittings, sealant, taps and drains, electrics and heating, and the outside. Write each problem as one line with a photo, rather than a general complaint, so each one can be fixed and ticked off.
Agree in your contract when each payment is due, and tie the last one to the snagging list being closed. Citizens Advice suggests paying in stages and being clear about the points in the work when payments are due. Keeping the final payment until the agreed snags are done gives both sides a clear finish line.
For work done under a consumer contract in England, Citizens Advice says the trader should fix a problem within a reasonable amount of time without causing too much inconvenience. The law does not define reasonable, so agree a date for each item in writing. For a new-build home, Which? says problems found in the first two years go back to the builder.
Yes. A snagging app, or a shared spreadsheet on a small job, works as long as every item records the room and spot, the problem, a photo, the trade, a fix-by date and a status that only you can close. It should be easy to use on a phone while you walk the rooms, and easy to share with the builder.
Real renovation experience and regional guidance from Operation Sicily.

A good payment schedule keeps your money roughly level with the work done. How to set the deposit, the stages and the final payment, how to pay safely, and what to record each time.

Before and after photos are more than a reveal. How to take matching shots room by room, what to record while the walls are open, and how the photos help with snags, neighbours, claims and a sale.

A written agreement with your builder does not need legal language. It needs the work, the price, the dates, the payments, how changes are handled and what happens at the end. Here is what to put in it.
Budgets, quotes, payments, documents and decisions in one place
30 days free. No card needed.
Monthly, with no annual plan. The Terms of membership set out the details.